Hanover County, VA: five data center proposals

Five data center proposals before one county in 29 months: Mountain Road (Tract) as anchor; Hunting Hawk (HHHunt), Iron Horse (Tradeport Hanover Land), Hickory Hill (Tract) and Old Ridge Road (LS Power)

Applicant / entity

Tract (Mountain Road and Hickory Hill); HHHunt (Hunting Hawk); Tradeport Hanover Land, L.L.C. / WestDulles Properties (Iron Horse); LS Power (Old Ridge Road)

Capacity

900 MW (Mountain Road); 2.4 GW (Hickory Hill)

Developer type

master-planned data center land developer

Jurisdiction

suburban-rural county, metro-adjacent

Status

Not approved

Last updated 7 September 2026. Public record reviewed through this date; digital layer from the most recent pull. This market is on a periodic refresh cadence. Member markets are re-scored on a set schedule.
Digital layer: Reddit and public record only. Search-volume data was not available for this scoring round, so per-category digital intensity is derived from the project-attributed Reddit corpus rather than cross-checked against keyword volume. Search behavior measures a different population than public posting does: people who look something up privately, so its absence is recorded here rather than treated as zero. The public-record half of every category is unaffected.

Sentiment

35/100

Mixed Not approved

Half of resamples fall between 34 and 36. Differences smaller than that are not meaningful.

Loudness
65Loud · 83 normalized, 81 per 10,000 residents, the basis on which this market compares to another
Scope
Concern sits at county; the venue acting on it is county.
hyper-local›county›regional›state›national
Veto point
Binding And exercised repeatedly in both directions. The same board approved Tract's 1,200-acre, 2.4 GW Hickory Hill campus UNANIMOUSLY in March 2024, then denied Tract's 430-acre, 900 MW Mountain Road campus 4-3 in May 2026. Hunting Hawk was denied and withdrawn. Iron Horse was recommended 5-2 for approval in August 2026 and awaits the Board.
Local sentiment not published. Local share 11% is below the 15% floor. The corpus is a state or regional subreddit, so its digital signal measures statewide salience, not local sentiment.

Where this market sits

Every market GridSight has scored, on sentiment against absolute loudness. A market can be quiet and negative, or loud and mixed. Those are different situations and they call for different responses. Loudness is scaled against fixed references rather than against the loudest market scored, so adding a market does not move anyone else's position.

2030405060406080100 SENTIMENT → better LOUDNESS → NashvilleSalineCharlotteEffinghamBox ElderMemphis metroRichlandCowetaNew Albany / LickingHanover
MarketSentimentLoudNorm ScopeVetoOutcome
Saline Township, MI298994county › statebindingNot approved ⚖
Nashville, TN317841hyper-local › countybindingNot approved ⚖
Hanover County, VA356583county › countybindingNot approved
Effingham County, GA376877county › statenoneApproved, contested
New Albany / Licking County, OH406363state › countybindingApproved, contested
Charlotte, NC417275hyper-local › countybindingDelayed
Coweta County, GA4184127county › countybindingApproved, contested ⚖
Box Elder County, UT449869state › statenoneDelayed
Memphis metro, TN / MS448661hyper-local › nationalconditionalApproved, contested ⚖
Richland Parish, LA517612state › statenoneApproved, contested

Concern categories

Concern runs 0-100 and higher is worse. Every row opens to its evidence and its public-record / digital split. The score is the inverse of the weighted mean across evidenced categories. Read it alongside the category count, not on its own.

▶Water 97

Dominant grievance and the only one a supervisor named as decisive. Stoneman: 'I do think the water concern is a valid issue here.' On record: 600,000 gpd avg / 2M gpd peak (Mountain Road), 700,000 gpd reserved (Hickory Hill), 10,500 gpd claimed (Hunting Hawk), closed-loop adopted (Iron Horse). Structural amplifier: Hanover buys 20 MGD from Richmond under a contract expiring June 2035 and suffered outages from Richmond's Jan 2025 plant failure; long-term fixes cost $424-543M.

Public record 95 · Digital 100 · weight 16.2% · 55 evidence items

▶Electricity / Grid Rate Impact 79

Strong at state level, thinner locally. Site facts: 900 MW each at Mountain Road and Hunting Hawk, 2.4 GW at Hickory Hill, a 500-kV line crossing Hunting Hawk. But the Nov 2025 SCC order created a 25 MW rate class with 14-year terms and exit fees, and the Aug 2026 order created GS-5 with directly assigned upgrades. No Hanover speaker was recorded making a specific quantified rate-impact claim.

Public record 70 · Digital 95 · weight 8.9% · 30 evidence items

▶Zoning / Process 73

Hanover decided three projects and is deciding a fourth with NO adopted data center ordinance; the county's own schedule does not reach Board adoption until December 2027. Resident: 'Standards first, approval second.' Comp-plan-amendment objection was the operative ground at Hunting Hawk. Process artifacts: capped 46-speaker registration with 69/69/69-minute allocations, a balloon test, an applicant deferral requested one hour before a hearing.

Public record 93 · Digital 35 · weight 15.4% · 52 evidence items

▶Jobs / Economic Benefit Credibility 70

Every figure is applicant- or supporter-supplied and they conflict. Mountain Road: 300-350 permanent (Tract); construction reported at 1,000 (developer) vs 1,100+ (attributed to a construction worker speaking in favor). Hunting Hawk: 'at least 420 jobs' with revenue reported as $8-12M/yr vs $6.5M then $11.9M/yr. Iron Horse 2026: no jobs figure at all. No independently verified employment or fiscal figure exists for any project. JLARC found 48c returned per $1 abated.

Public record 68 · Digital 73 · weight 10.0% · 34 evidence items

▶Rural Character / Conservation Land 67

Named as the operative reason for the Hunting Hawk denial: the commission found it 'did not fit Hanover's rural character.' Tract's $6M conservation/parks/Chickahominy-trail proffer was a direct response. Bundled with the Ashcake Landfill and the 1,300-acre Luck Stone quarry at the 22 Apr 2026 Earth Day rally, so the conservation frame is broader than data centers.

Public record 90 · Digital 24 · weight 14.2% · 48 evidence items

▶Noise 58

Consistently raised, never quantified by the county. Neighbors For Change documented low-frequency noise and 300 diesel generators at 75-150 monthly testing hours, but that is an advocacy-source claim. No Hanover noise study, no adopted decibel limit, no measured data. Score capped by the total absence of local measurement.

Public record 72 · Digital 31 · weight 6.5% · 22 evidence items

▶Anti-corporate sentiment 54

Present in tone, rarely explicit. Petition: 'nowhere in our community is safe from industrial development.' NAACP chapter president: 'Our community's heartbeat is more important than a data center.' Structurally reinforced by the absent-tenant problem: no tenant was ever named for any of the three contested projects, and opponents objected to the 'speculative nature with unknown end user.'

Public record 55 · Digital 52 · weight 4.7% · 16 evidence items

▶Traffic 48

Raised at every hearing and decisive in 2024; Commissioner Abbott: 'Right now, I think the traffic is a problem.' ~1,500 daily trips at Mountain Road. The counter-argument is on record and used by applicants: Condlin argued data centers are 'a better option because it's less traffic' against a by-right mixed-use alternative, and the HHHunt residential replacement generates 1,000 daily trips itself.

Public record 60 · Digital 27 · weight 5.9% · 20 evidence items

▶Wildlife / Land 40

Land-conversion evidence is solid; wildlife evidence is thin. 427-430 acres mostly undeveloped and wooded; 1,200 acres at Hickory Hill; Earth Day rally focused on woodland and wetland destruction. Wildlife proper appears essentially once. No habitat study, no species claim, no wetlands delineation dispute located.

Public record 45 · Digital 31 · weight 4.1% · 14 evidence items

▶Health 31

Weakly evidenced locally. Only proximate claims: Mayers on pollution/emissions, Bruner on 'contaminated vapor,' Neighbors For Change on low-frequency noise. No health study, no DEQ air permit dispute, no medical testimony entered the Hanover record.

Public record 30 · Digital 34 · weight 2.7% · 9 evidence items

▶Cross-market spillover 30

The 17 Nov 2025 community meeting drew 450+ residents from Hanover, Henrico AND Goochland; Henrico Citizen headlined 'hundreds of Henrico, Hanover residents.' The Dominion Club's GM and Wyndham residents formally opposed a project in a neighboring county. Tract carried the fight into Goochland by July 2026. Both articles carrying the strongest evidence are paywalled, which caps confidence.

Public record 45 · Digital 2 · weight 3.0% · 12 evidence items

▶Schools / Children 25

Polarity is inverted, the market's most counterintuitive finding. The only substantive on-record schools argument is PRO-data-center: Commissioner Leadbetter, 'It eliminates burden on schools, EMS and law enforcement.' No Hanover parent, teacher or school board member is quoted, and Hanover County Public Schools took no position.

Public record 25 · Digital 25 · weight 2.1% · 7 evidence items

▶Property Values 23

Listed among concerns at the May 2026 Board hearing and Floyd raised building-to-home proximity buffers. But not a single Hanover speaker is quoted anywhere making a property-value claim, no appraisal study, no realtor testimony, no assessment data entered the record. Present as a category label, absent as evidence.

Public record 35 · Digital 0 · weight 2.4% · 8 evidence items

▶Anti-AI sentiment 23

Essentially no evidence found. Across every hearing account, rally report, petition text and quoted resident statement retrieved, AI is not mentioned once. The nearest adjacent sentiment is technological-obsolescence scepticism: Walton, 'Data centers is something that's going to be obsolete in five to eight years from now.'

Public record 8 · Digital 50 · weight 2.0% · 4 evidence items

▶NDAs / Secrecy 21

Largely a no-evidence-found result and the record actively cuts against it. No Hanover NDA, confidentiality agreement, FOIA dispute or closed-session controversy located. Supervisor Dibble: 'I believe it's transparent, and this process makes a good project better.' What exists is the weaker adjacent grievance of no named end user.

Public record 20 · Digital 24 · weight 2.0% · 6 evidence items