A GridSight tracker · Updated 16 November 2026
A moratorium is a temporary pause on new data center approvals while a community writes its rules. 1,101 have been recorded across the country, and 946 are still in place. Here is what happened in the 79 that have ended.
Of 79 moratoriums that have ended, 50 ended with rules that let projects move forward under new standards. 10 became bans.
If your board is weighing a pause, start with what nearby counties did: how long they paused, and what rules they adopted when it ended.
Brief your boardLook up your state to see whether your community has paused new data centers, and when the pause ends.
Find your state →Nine in ten pauses start because a county has no rules for a project this large. You can see what neighboring counties adopted and share it with the counties in your territory while their rules are still being written.
Brief a countyA moratorium can hold up an application for six months to a year, and sometimes longer. Check the places on your short list here, and use the list below to see which pauses end next and what rules tend to follow.
Screen a parcelBefore a project goes into your model, look up its jurisdiction here. A local pause puts the schedule at risk, and it is easier to price at the start than to find late in diligence.
Get a risk read55 moratoriums are scheduled to end by Feb 14, 2027. Many will be extended, so read each date as the next decision point.
Most recent first. “What changed” summarizes the rules or action that replaced the pause.
Showing all 79
| Place | Paused | Ended | Outcome | What changed |
|---|---|---|---|---|
| ScarboroughMaine | Jun 2026 | Nov 2026 | Rules adopted | New zoning restrictions |
| Sioux CountyIowa | 2025 | Oct 2026 | Rules adopted | County data center rules adopted |
| Imperial CountyCalifornia | Jun 2026 | Oct 2026 | Struck down | Repealed under a court order |
| Augusta-Richmond CountyGeorgia | Jun 2026 | Oct 2026 | Rules adopted | Buffer rules, with some exceptions |
| WixomMichigan | Mar 2026 | Sep 2026 | Rules adopted | Special land use in industrial districts; noise studies; utility checks |
| RoswellGeorgia | Jan 2026 | Sep 2026 | Lapsed, no new rules | Expired after two extensions; no rules adopted |
| Oglethorpe CountyGeorgia | Jul 2026 | Sep 2026 | Rules adopted | Restrictive data center ordinance |
| Morton CountyNorth Dakota | Sep 2024 | Sep 2026 | Rules adopted | Equipment about 3/4 mile from homes; closed loop cooling; reclamation bond |
| Heard CountyGeorgia | Mar 2026 | Sep 2026 | Lapsed, no new rules | Expired; no rules found |
| FederalsburgMaryland | Aug 2026 | Sep 2026 | Became a ban | Banned in every zoning district |
| CovingtonGeorgia | Jan 2026 | Sep 2026 | Rules adopted | Data center ordinance adopted, pause revoked |
| Colleton CountySouth Carolina | Jul 2026 | Sep 2026 | Rules adopted | Lifted in industrial zones and west of I-95; still paused elsewhere |
| ChillicotheOhio | Aug 2026 | Sep 2026 | Struck down | Repealed after an earlier zoning approval letter surfaced |
| South FultonGeorgia | Dec 2025 | Aug 2026 | Rules adopted | 20 acre minimum lot; industrial zones only; buffers |
| Smithfield TownshipPennsylvania | May 2026 | Aug 2026 | Rules adopted | Confined to a new heavy industrial district |
| Shelby CountyIndiana | Feb 2026 | Aug 2026 | Rules adopted | Data center overlay district |
| NortonOhio | Dec 2025 | Aug 2026 | Rules adopted | Special industrial use permits for large data centers |
| Mercer CountyNorth Dakota | Mar 2026 | Aug 2026 | Rules adopted | County data center zoning ordinance |
| McPherson CountyKansas | Aug 2025 | Aug 2026 | Became a ban | Banned outside city limits |
| MassillonOhio | Apr 2026 | Aug 2026 | Rules adopted | Heavy industrial only; 400 ft from homes; utility and noise certifications |
| Leavenworth CountyKansas | May 2026 | Aug 2026 | Lapsed, no new rules | Extension failed; decision left to the new commission |
| Floyd CountyGeorgia | Jun 2026 | Aug 2026 | Rules adopted | Heavy industrial only; 600 ft from homes; water and noise limits |
| CoachellaCalifornia | Jun 2026 | Aug 2026 | Became a ban | Citywide prohibition |
| Miami CountyIndiana | May 2026 | Jul 2026 | Rules adopted | Allowed in industrial and business zones; 55 dB limit; closed loop or air cooling |
| Marion CountyMissouri | Jun 2026 | Jul 2026 | Rules adopted | Industrial zoning for projects of 5 MW and up; environmental agreement |
| Clark TownshipMichigan | Jun 2025 | Jul 2026 | Rules adopted | 30 page ordinance on siting and operations |
| AshlandKentucky | Feb 2026 | Jul 2026 | Rules adopted | Conditional use zoning |
| WatervilleOhio | Dec 2025 | Jun 2026 | Lapsed, no new rules | Expired; conditional use process under review |
| Troup CountyGeorgia | Sep 2025 | Jun 2026 | Rules adopted | Industrial only; 1,500 ft from homes and schools; closed loop cooling |
| ShutesburyMassachusetts | Sep 2025 | Jun 2026 | Lapsed, no new rules | Expired; no bylaw adopted |
| Polk CountyGeorgia | Mar 2026 | Jun 2026 | Rules adopted | Permanent zoning for commercial and heavy industrial districts |
| MayodanNorth Carolina | May 2026 | Jun 2026 | Rules adopted | Zoning rules for data processing facilities |
| Logan CountyIllinois | May 2026 | Jun 2026 | Struck down | Ruled procedurally invalid |
| Lenox TownshipMichigan | Feb 2026 | Jun 2026 | Lapsed, no new rules | Expired; ordinance work stalled |
| Jerome TownshipOhio | Sep 2025 | Jun 2026 | Rules adopted | Conditional use; 300 ft from homes; screening berms |
| Hill CountyTexas | May 2026 | Jun 2026 | Struck down | Rescinded after a $100 million developer lawsuit; review rules adopted |
| Dundee TownshipMichigan | Dec 2025 | Jun 2026 | Lapsed, no new rules | Expired; ordinance still in workshop |
| BirminghamAlabama | Mar 2026 | Jun 2026 | Rules adopted | Permanent data center zoning adopted |
| St. CharlesMissouri | Aug 2025 | May 2026 | Became a ban | Citywide prohibition |
| JonesboroughTennessee | Nov 2025 | May 2026 | Rules adopted | Data center zoning amendments |
| IrontonOhio | Feb 2026 | May 2026 | Rules adopted | Data center zoning ordinance |
| GriffinGeorgia | Jan 2026 | May 2026 | Rules adopted | Special use permit; 1,000 to 1,500 ft from homes; no hyperscale campuses |
| BrevardNorth Carolina | Mar 2026 | May 2026 | Rules adopted | Industrial zones only; conditional rezoning case by case |
| Paris TownshipOhio | Feb 2026 | Apr 2026 | Became a ban | No permitted or conditional use in any district |
| Oliver CountyNorth Dakota | Mar 2026 | Apr 2026 | Lapsed, no new rules | Lifted when an application arrived; draft rules pending |
| Montour CountyPennsylvania | Nov 2025 | Apr 2026 | Rules adopted | Conditional use in industrial district; setbacks; noise and lighting limits |
| Monterey ParkCalifornia | Jan 2026 | Apr 2026 | Became a ban | Citywide prohibition, approved by voters with 88% |
| Monroe CountyGeorgia | Dec 2025 | Apr 2026 | Rules adopted | Special use in light industrial; 500 ft buffer; no well water |
| MasonMichigan | Jan 2026 | Apr 2026 | Lapsed, no new rules | New district adopted, then repealed after a citizen petition |
| Marshall CountyIndiana | Feb 2025 | Apr 2026 | Became a ban | Countywide ban |
| LaGrangeGeorgia | Sep 2025 | Apr 2026 | Rules adopted | Special use permit in industrial zones, decided case by case |
| La GrangeKentucky | Jun 2025 | Apr 2026 | Lapsed, no new rules | Expired after one extension; no rules adopted |
| Athens-Clarke CountyGeorgia | Dec 2025 | Apr 2026 | Rules adopted | Heavy industrial zones only; closed loop cooling |
| MontebelloCalifornia | Feb 2026 | Mar 2026 | Lapsed, no new rules | Expired; staff still drafting standards |
| FayettevilleGeorgia | Jan 2026 | Mar 2026 | Became a ban | Prohibited in every zoning district |
| AuroraIllinois | Sep 2025 | Mar 2026 | Rules adopted | Council approval; water and energy plans; noise limits; no evaporative cooling |
| White CountyIndiana | Oct 2025 | Feb 2026 | Rules adopted | Water, noise, setback and emergency response rules |
| Logan CountyColorado | Oct 2025 | Feb 2026 | Rules adopted | County data center facility regulations |
| Social CircleGeorgia | Sep 2025 | Jan 2026 | Rules adopted | Special use permit; impact study; noise standards |
| Jones CountyGeorgia | Sep 2025 | Jan 2026 | Rules adopted | Industrial only; 200 to 400 ft setbacks; noise limits; closed loop cooling |
| Iron CountyUtah | 2026 | 2026 | Rules adopted | County data center ordinance |
| Fluvanna CountyVirginia | Sep 2025 | 2026 | Rules adopted | Special use permit in industrial zones, no longer by right |
| DrydenNew York | Jul 2024 | 2026 | Became a ban | Not allowed in any zoning district |
| Pike CountyGeorgia | Sep 2025 | Dec 2025 | Rules adopted | 10 acre minimum lot; 50 ft buffer; 65 dB limit; decommissioning bond |
| Coweta CountyGeorgia | May 2025 | Dec 2025 | Rules adopted | Permanent data center ordinance |
| Kootenai CountyIdaho | Mar 2025 | Oct 2025 | Rules adopted | Industrial zones by permit; none over the aquifer |
| NiagaraNew York | Sep 2024 | Sep 2025 | Lapsed, no new rules | Expired |
| Dorrance TownshipPennsylvania | Aug 2025 | Sep 2025 | Rules adopted | Conditional use standards for noise, traffic and water |
| Douglas CountyGeorgia | Mar 2025 | Jun 2025 | Lapsed, no new rules | Expired; projects go through normal rezoning |
| Hitchcock CountyNebraska | Feb 2025 | Mar 2025 | Rules adopted | Conditional use in agricultural and commercial districts |
| Jones CountyIowa | Oct 2024 | 2025 | Rules adopted | Special use permit ordinance |
| PeculiarMissouri | Aug 2024 | Oct 2024 | Became a ban | Data centers removed from the zoning code |
| Williams CountyNorth Dakota | Jun 2023 | 2024 | Rules adopted | Conditional use; 1 mile from homes and schools; 3 miles between data centers |
| HarrisonArkansas | May 2023 | Nov 2023 | Struck down | Repealed amid litigation concerns |
| FairbornOhio | Sep 2022 | Mar 2023 | Lapsed, no new rules | Expired; a new pause was adopted in 2026 |
| GrotonConnecticut | Jun 2022 | 2023 | Rules adopted | Caps data centers at 12,500 sq ft, with siting and operating limits |
| WenatcheeWashington | Feb 2018 | 2019 | Rules adopted | Permanent rules for data centers and crypto mining |
| Moses LakeWashington | May 2018 | 2019 | Rules adopted | Permanent code for server farms and data centers |
| East WenatcheeWashington | Mar 2018 | 2019 | Rules adopted | Utility load verification; electrical permits |
946 moratoriums remain in place across 47 states. These are the 13 states with 25 or more.
Plus 286 more across 34 other states.
A data center moratorium is a temporary pause on accepting, reviewing or approving new data center applications. Local governments usually adopt one when they have no zoning rules for projects this large and need time to write them. Most apply to new applications, not to projects that already hold approvals.
A moratorium is temporary. It pauses new data center applications for a set term, typically 180 days, while a community writes its rules. A ban is a permanent prohibition. Of the 79 moratoriums we have tracked to an end, 10 became bans, and 50 ended with rules that let projects move forward under new standards.
The typical first term is 180 days, and about 78% run between three months and a year. Many are extended at least once. Of the moratoriums we track, 134 have been extended.
Of the 79 we have tracked to an end, 63% ended with new rules that allow data centers under standards such as industrial zoning, setbacks from homes, noise limits and water requirements. 18% lapsed or were lifted without new rules, 13% became permanent bans, and 6% were struck down or repealed under legal pressure.
Yes. 5 of the 79 ended that way. Hill County, Texas rescinded its moratorium after a developer filed a $100 million federal lawsuit, Imperial County, California repealed its pause under a court order, and a court found Logan County, Illinois adopted its pause improperly.
Ohio and Michigan lead, with 150 and 121 still in place, followed by North Carolina, Georgia and Iowa.
The underlying records come from Moratorium Nation, an open dataset of local moratoriums compiled by Michael J. Bommarito and published under a Creative Commons Attribution license. We used the 1,103 records that cover data centers.
For each data center moratorium the dataset records as ended, we read the record and coded what replaced the pause. We set aside ten that were unclear or simply replaced by a new pause, counted Oliver County, North Dakota once although it paused three times, and added two that ended after the dataset’s most recent review: Sioux County, Iowa and Iron County, Utah. The share of moratoriums that started over missing local rules comes from the dataset’s own trigger coding.
Two cautions. Most moratoriums have not ended yet, so these shares will move as more expire. And Georgia accounts for 19 of the 79, because its pauses started earlier. “What changed” is our summary of the adopted rules, so check the local ordinance before relying on it. End dates in the 90 day list are scheduled dates, and extensions are common.
The GridSight, “Data center moratoriums: what happens when the pause ends,” updated 8 November 2026, thegridsight.com/data-center-moratoriums. Based on Moratorium Nation (CC BY 4.0).
The GridSight reads the public record and local search in the places you are watching, so you know what the rules are likely to require before they are written.