Data center moratoriums:946 in place, and what happens when the pause ends.

A moratorium is a temporary pause on new data center approvals while a community writes its rules. 1,101 have been recorded across the country, and 946 are still in place. Here is what happened in the 79 that have ended.

When the pause ends, rules usually follow.

Of 79 moratoriums that have ended, 50 ended with rules that let projects move forward under new standards. 10 became bans.

  • 63% Rules adopted (50)
  • 18% Lapsed, no new rules (14)
  • 13% Became a ban (10)
  • 6% Struck down (5)
9 in 10moratoriums started because local rules did not exist yet
180 daysis the typical first term
946still in place across 47 states

What this means for you

Counties and local officials

If your board is weighing a pause, start with what nearby counties did: how long they paused, and what rules they adopted when it ended.

Brief your board
Residents

Look up your state to see whether your community has paused new data centers, and when the pause ends.

Find your state →
Utilities

Nine in ten pauses start because a county has no rules for a project this large. You can see what neighboring counties adopted and share it with the counties in your territory while their rules are still being written.

Brief a county
Developers

A moratorium can hold up an application for six months to a year, and sometimes longer. Check the places on your short list here, and use the list below to see which pauses end next and what rules tend to follow.

Screen a parcel
Investors

Before a project goes into your model, look up its jurisdiction here. A local pause puts the schedule at risk, and it is easier to price at the start than to find late in diligence.

Get a risk read

Ending in the next 90 days

55 moratoriums are scheduled to end by Feb 14, 2027. Many will be extended, so read each date as the next decision point.

All 79 moratoriums that have ended

Most recent first. “What changed” summarizes the rules or action that replaced the pause.

Showing all 79

PlacePausedEndedOutcomeWhat changed
ScarboroughMaineJun 2026Nov 2026Rules adoptedNew zoning restrictions
Sioux CountyIowa2025Oct 2026Rules adoptedCounty data center rules adopted
Imperial CountyCaliforniaJun 2026Oct 2026Struck downRepealed under a court order
Augusta-Richmond CountyGeorgiaJun 2026Oct 2026Rules adoptedBuffer rules, with some exceptions
WixomMichiganMar 2026Sep 2026Rules adoptedSpecial land use in industrial districts; noise studies; utility checks
RoswellGeorgiaJan 2026Sep 2026Lapsed, no new rulesExpired after two extensions; no rules adopted
Oglethorpe CountyGeorgiaJul 2026Sep 2026Rules adoptedRestrictive data center ordinance
Morton CountyNorth DakotaSep 2024Sep 2026Rules adoptedEquipment about 3/4 mile from homes; closed loop cooling; reclamation bond
Heard CountyGeorgiaMar 2026Sep 2026Lapsed, no new rulesExpired; no rules found
FederalsburgMarylandAug 2026Sep 2026Became a banBanned in every zoning district
CovingtonGeorgiaJan 2026Sep 2026Rules adoptedData center ordinance adopted, pause revoked
Colleton CountySouth CarolinaJul 2026Sep 2026Rules adoptedLifted in industrial zones and west of I-95; still paused elsewhere
ChillicotheOhioAug 2026Sep 2026Struck downRepealed after an earlier zoning approval letter surfaced
South FultonGeorgiaDec 2025Aug 2026Rules adopted20 acre minimum lot; industrial zones only; buffers
Smithfield TownshipPennsylvaniaMay 2026Aug 2026Rules adoptedConfined to a new heavy industrial district
Shelby CountyIndianaFeb 2026Aug 2026Rules adoptedData center overlay district
NortonOhioDec 2025Aug 2026Rules adoptedSpecial industrial use permits for large data centers
Mercer CountyNorth DakotaMar 2026Aug 2026Rules adoptedCounty data center zoning ordinance
McPherson CountyKansasAug 2025Aug 2026Became a banBanned outside city limits
MassillonOhioApr 2026Aug 2026Rules adoptedHeavy industrial only; 400 ft from homes; utility and noise certifications
Leavenworth CountyKansasMay 2026Aug 2026Lapsed, no new rulesExtension failed; decision left to the new commission
Floyd CountyGeorgiaJun 2026Aug 2026Rules adoptedHeavy industrial only; 600 ft from homes; water and noise limits
CoachellaCaliforniaJun 2026Aug 2026Became a banCitywide prohibition
Miami CountyIndianaMay 2026Jul 2026Rules adoptedAllowed in industrial and business zones; 55 dB limit; closed loop or air cooling
Marion CountyMissouriJun 2026Jul 2026Rules adoptedIndustrial zoning for projects of 5 MW and up; environmental agreement
Clark TownshipMichiganJun 2025Jul 2026Rules adopted30 page ordinance on siting and operations
AshlandKentuckyFeb 2026Jul 2026Rules adoptedConditional use zoning
WatervilleOhioDec 2025Jun 2026Lapsed, no new rulesExpired; conditional use process under review
Troup CountyGeorgiaSep 2025Jun 2026Rules adoptedIndustrial only; 1,500 ft from homes and schools; closed loop cooling
ShutesburyMassachusettsSep 2025Jun 2026Lapsed, no new rulesExpired; no bylaw adopted
Polk CountyGeorgiaMar 2026Jun 2026Rules adoptedPermanent zoning for commercial and heavy industrial districts
MayodanNorth CarolinaMay 2026Jun 2026Rules adoptedZoning rules for data processing facilities
Logan CountyIllinoisMay 2026Jun 2026Struck downRuled procedurally invalid
Lenox TownshipMichiganFeb 2026Jun 2026Lapsed, no new rulesExpired; ordinance work stalled
Jerome TownshipOhioSep 2025Jun 2026Rules adoptedConditional use; 300 ft from homes; screening berms
Hill CountyTexasMay 2026Jun 2026Struck downRescinded after a $100 million developer lawsuit; review rules adopted
Dundee TownshipMichiganDec 2025Jun 2026Lapsed, no new rulesExpired; ordinance still in workshop
BirminghamAlabamaMar 2026Jun 2026Rules adoptedPermanent data center zoning adopted
St. CharlesMissouriAug 2025May 2026Became a banCitywide prohibition
JonesboroughTennesseeNov 2025May 2026Rules adoptedData center zoning amendments
IrontonOhioFeb 2026May 2026Rules adoptedData center zoning ordinance
GriffinGeorgiaJan 2026May 2026Rules adoptedSpecial use permit; 1,000 to 1,500 ft from homes; no hyperscale campuses
BrevardNorth CarolinaMar 2026May 2026Rules adoptedIndustrial zones only; conditional rezoning case by case
Paris TownshipOhioFeb 2026Apr 2026Became a banNo permitted or conditional use in any district
Oliver CountyNorth DakotaMar 2026Apr 2026Lapsed, no new rulesLifted when an application arrived; draft rules pending
Montour CountyPennsylvaniaNov 2025Apr 2026Rules adoptedConditional use in industrial district; setbacks; noise and lighting limits
Monterey ParkCaliforniaJan 2026Apr 2026Became a banCitywide prohibition, approved by voters with 88%
Monroe CountyGeorgiaDec 2025Apr 2026Rules adoptedSpecial use in light industrial; 500 ft buffer; no well water
MasonMichiganJan 2026Apr 2026Lapsed, no new rulesNew district adopted, then repealed after a citizen petition
Marshall CountyIndianaFeb 2025Apr 2026Became a banCountywide ban
LaGrangeGeorgiaSep 2025Apr 2026Rules adoptedSpecial use permit in industrial zones, decided case by case
La GrangeKentuckyJun 2025Apr 2026Lapsed, no new rulesExpired after one extension; no rules adopted
Athens-Clarke CountyGeorgiaDec 2025Apr 2026Rules adoptedHeavy industrial zones only; closed loop cooling
MontebelloCaliforniaFeb 2026Mar 2026Lapsed, no new rulesExpired; staff still drafting standards
FayettevilleGeorgiaJan 2026Mar 2026Became a banProhibited in every zoning district
AuroraIllinoisSep 2025Mar 2026Rules adoptedCouncil approval; water and energy plans; noise limits; no evaporative cooling
White CountyIndianaOct 2025Feb 2026Rules adoptedWater, noise, setback and emergency response rules
Logan CountyColoradoOct 2025Feb 2026Rules adoptedCounty data center facility regulations
Social CircleGeorgiaSep 2025Jan 2026Rules adoptedSpecial use permit; impact study; noise standards
Jones CountyGeorgiaSep 2025Jan 2026Rules adoptedIndustrial only; 200 to 400 ft setbacks; noise limits; closed loop cooling
Iron CountyUtah20262026Rules adoptedCounty data center ordinance
Fluvanna CountyVirginiaSep 20252026Rules adoptedSpecial use permit in industrial zones, no longer by right
DrydenNew YorkJul 20242026Became a banNot allowed in any zoning district
Pike CountyGeorgiaSep 2025Dec 2025Rules adopted10 acre minimum lot; 50 ft buffer; 65 dB limit; decommissioning bond
Coweta CountyGeorgiaMay 2025Dec 2025Rules adoptedPermanent data center ordinance
Kootenai CountyIdahoMar 2025Oct 2025Rules adoptedIndustrial zones by permit; none over the aquifer
NiagaraNew YorkSep 2024Sep 2025Lapsed, no new rulesExpired
Dorrance TownshipPennsylvaniaAug 2025Sep 2025Rules adoptedConditional use standards for noise, traffic and water
Douglas CountyGeorgiaMar 2025Jun 2025Lapsed, no new rulesExpired; projects go through normal rezoning
Hitchcock CountyNebraskaFeb 2025Mar 2025Rules adoptedConditional use in agricultural and commercial districts
Jones CountyIowaOct 20242025Rules adoptedSpecial use permit ordinance
PeculiarMissouriAug 2024Oct 2024Became a banData centers removed from the zoning code
Williams CountyNorth DakotaJun 20232024Rules adoptedConditional use; 1 mile from homes and schools; 3 miles between data centers
HarrisonArkansasMay 2023Nov 2023Struck downRepealed amid litigation concerns
FairbornOhioSep 2022Mar 2023Lapsed, no new rulesExpired; a new pause was adopted in 2026
GrotonConnecticutJun 20222023Rules adoptedCaps data centers at 12,500 sq ft, with siting and operating limits
WenatcheeWashingtonFeb 20182019Rules adoptedPermanent rules for data centers and crypto mining
Moses LakeWashingtonMay 20182019Rules adoptedPermanent code for server farms and data centers
East WenatcheeWashingtonMar 20182019Rules adoptedUtility load verification; electrical permits

Still paused, by state

946 moratoriums remain in place across 47 states. These are the 13 states with 25 or more.

Plus 286 more across 34 other states.

Questions

What is a data center moratorium?

A data center moratorium is a temporary pause on accepting, reviewing or approving new data center applications. Local governments usually adopt one when they have no zoning rules for projects this large and need time to write them. Most apply to new applications, not to projects that already hold approvals.

What is the difference between a data center moratorium and a ban?

A moratorium is temporary. It pauses new data center applications for a set term, typically 180 days, while a community writes its rules. A ban is a permanent prohibition. Of the 79 moratoriums we have tracked to an end, 10 became bans, and 50 ended with rules that let projects move forward under new standards.

How long do data center moratoriums last?

The typical first term is 180 days, and about 78% run between three months and a year. Many are extended at least once. Of the moratoriums we track, 134 have been extended.

What happens when a data center moratorium ends?

Of the 79 we have tracked to an end, 63% ended with new rules that allow data centers under standards such as industrial zoning, setbacks from homes, noise limits and water requirements. 18% lapsed or were lifted without new rules, 13% became permanent bans, and 6% were struck down or repealed under legal pressure.

Can a data center moratorium be challenged in court?

Yes. 5 of the 79 ended that way. Hill County, Texas rescinded its moratorium after a developer filed a $100 million federal lawsuit, Imperial County, California repealed its pause under a court order, and a court found Logan County, Illinois adopted its pause improperly.

Which states have the most data center moratoriums?

Ohio and Michigan lead, with 150 and 121 still in place, followed by North Carolina, Georgia and Iowa.

How we built this

The underlying records come from Moratorium Nation, an open dataset of local moratoriums compiled by Michael J. Bommarito and published under a Creative Commons Attribution license. We used the 1,103 records that cover data centers.

For each data center moratorium the dataset records as ended, we read the record and coded what replaced the pause. We set aside ten that were unclear or simply replaced by a new pause, counted Oliver County, North Dakota once although it paused three times, and added two that ended after the dataset’s most recent review: Sioux County, Iowa and Iron County, Utah. The share of moratoriums that started over missing local rules comes from the dataset’s own trigger coding.

Two cautions. Most moratoriums have not ended yet, so these shares will move as more expire. And Georgia accounts for 19 of the 79, because its pauses started earlier. “What changed” is our summary of the adopted rules, so check the local ordinance before relying on it. End dates in the 90 day list are scheduled dates, and extensions are common.

Cite this tracker

The GridSight, “Data center moratoriums: what happens when the pause ends,” updated 8 November 2026, thegridsight.com/data-center-moratoriums. Based on Moratorium Nation (CC BY 4.0).